A place where restoration project-type threads can go to avoid falling off the main page in the WIX hangar. Feel free to start threads on Restoration projects and/or warbird maintenance here. Named in memoriam for Gary Austin, a good friend of the site and known as RetroAviation here. He will be sorely missed.
Post a reply

Re: Yankee Air Museum - B-24 Display Project Thread

Thu Jul 28, 2016 5:49 pm

End of July Update

We have recently received parts necessary to start the repair process of the rear bomb bay side panels. Sections of Y36-48 zee stringer were fabricated in a press brake at a local shop. After the zee stringers were completed, the Longeron sections were formed at eight foot lengths. It was best for fabrication to remove the physical splices of the four panel subassemblies, Items 19 to 27 and 20 to 28. Before we can position the Longeron sections, we need to repair the lower scraped channels of the Station 5.1 rear wing spar bulkhead. Currently, we have placed the left splice section, locating holes, and splice plates. The left and right channel repairs could be completed by early next week. I’m hoping to have the Longeron sections in place by Thunder.

Batch of Y36-48 Stringers
Image

Station 5.1 Splice
Image

120 Ton Press Brake at a near by shop
Image
Last edited by ChrisAldridge on Sun Oct 02, 2016 12:40 pm, edited 1 time in total.

Re: Yankee Air Museum - B-24 Display Project Thread

Mon Sep 19, 2016 5:50 pm

September Update on the project

We have attached the left longeron and have completed three of the stringer splices, work is progressing. I'll post current photos soon.

Re: Yankee Air Museum - B-24 Display Project Thread

Tue Sep 20, 2016 6:20 am

Awesome thread Chris, always appreciate the updates. pop2

That brake certainly looks the business! Doesn't it? :shock:

Andy

Re: Yankee Air Museum - B-24 Display Project Thread

Sun Oct 02, 2016 2:22 pm

Early October Update

In September the team completed the mounting of the left side longeron piece. Originally this section of the GK32B2013 longeron assembly was two pieces with a splice at Station 5.2. We have made a single eight foot section to reduce work by the outside fabrication shop. In the future, a splice could be added from the longeron section at the Station 5.0 area. Since we are not able to rivet the longeron flange to new channel splice, they're advantages of using bolts. At the end of September, the team only has three vertical stringer splices left to install for the left side.

Image

Image

Image

Image

Re: Yankee Air Museum - B-24 Display Project Thread

Tue Oct 04, 2016 10:41 pm

Left Side Panel Photo Update – October 3rd, 2016

Image

Image

Re: Yankee Air Museum - B-24 Display Project Thread

Tue Nov 15, 2016 6:53 pm

Man I am grateful for people with the patience to do this work - I am impressed!

Tom P.

Re: Yankee Air Museum - B-24 Display Project Thread

Sun Nov 20, 2016 10:04 am

wendovertom wrote:Man I am grateful for people with the patience to do this work - I am impressed!

Tom P.


No doubt, it takes so much patience and vision to tackle a project like this.

Re: Yankee Air Museum - B-24 Display Project Thread

Fri Dec 09, 2016 2:19 am

Thank you for your kind words and support.

The project display has served to cover the WW-II theme of the current museum floor well. The tail section had quite of a life story from the crash to when the project was reset. I did not believe we could have rebuilt the waist gun area and forward without completely removing the upper PB4Y-2 Longeron on each side, since the fire warped the sections out of fuselage contour line. The fire and salvage operation damaged the formers around the teardrop turrets and in front. Everything above the main lower Longeron sections and in front of Station 7.3 was unusable for the first project team. Stringers of the fuselage bottom near Station 6.2 were crushed a foot in from the salvaged end of the tail fuselage. We could have rebuilt the roofline and waist gun areas, but it was agreed to join the sections was the best option to save either from the obvious.

The team is currently only able to work one day per week, but we are very excited to work when we can. Just last week, the crews have completed the vertical stringer splices for the bomb bay side panels. Before we can skin the sides, we must complete the installation of the track sections on the Station 6.0 bulkhead. After the track is positioned, the web reinforcements can then be cut and installed.

Moving forward, the bomb bay skinning could start before the end of the year. At the Longeron area, the bay doors close flush with a set of fairings mounted to the Longeron’s on each side. The fairings terminate the lower structure of the side panels, and were completed in November. I would like to try and investigate the microfilm drawings for the attaching brackets with the Inventor CAD model in progress. Once the fairings are installed, the project will have finished the currently planned major structural repair work. :)

The next update will cover design and fabrication of B-24 specific metal items. I wanted to share lessons learned and thoughts of aircraft stampings, as I had very little working knowledge to start.

Re: Yankee Air Museum - B-24 Display Project Thread

Fri Apr 07, 2017 3:17 pm

Great job Chris, any updates to share?

Re: Yankee Air Museum - B-24 Display Project Thread

Wed Dec 26, 2018 6:25 pm

End of 2018 Update:

I've wanted to provide an update since last posting for quite sometime. Activity have since slowed, but not completely stopped. The majority of structural work is complete with minor details of the Station 6.0 bulkhead remaining. With the museum exhibit space becoming more compact, providing project photos is now more difficult. I'll provide a new update before then end of the year.

Image

Re: Yankee Air Museum - B-24 Display Project Thread

Fri Dec 28, 2018 9:47 am

Thank you for posting the pictures. Very interested in the progress.

Re: Yankee Air Museum - B-24 Display Project Thread

Wed Feb 06, 2019 6:42 pm

Thank you for the update!

Re: Yankee Air Museum - B-24 Display Project Thread

Fri Jan 17, 2020 2:47 pm

Been a little while. Any updates to share?!?!! :D