Re: Yankee Air Museum - B-24 Display Project Thread
Posted: Thu Jul 28, 2016 5:49 pm
End of July Update
We have recently received parts necessary to start the repair process of the rear bomb bay side panels. Sections of Y36-48 zee stringer were fabricated in a press brake at a local shop. After the zee stringers were completed, the Longeron sections were formed at eight foot lengths. It was best for fabrication to remove the physical splices of the four panel subassemblies, Items 19 to 27 and 20 to 28. Before we can position the Longeron sections, we need to repair the lower scraped channels of the Station 5.1 rear wing spar bulkhead. Currently, we have placed the left splice section, locating holes, and splice plates. The left and right channel repairs could be completed by early next week. I’m hoping to have the Longeron sections in place by Thunder.
Batch of Y36-48 Stringers

Station 5.1 Splice

120 Ton Press Brake at a near by shop

We have recently received parts necessary to start the repair process of the rear bomb bay side panels. Sections of Y36-48 zee stringer were fabricated in a press brake at a local shop. After the zee stringers were completed, the Longeron sections were formed at eight foot lengths. It was best for fabrication to remove the physical splices of the four panel subassemblies, Items 19 to 27 and 20 to 28. Before we can position the Longeron sections, we need to repair the lower scraped channels of the Station 5.1 rear wing spar bulkhead. Currently, we have placed the left splice section, locating holes, and splice plates. The left and right channel repairs could be completed by early next week. I’m hoping to have the Longeron sections in place by Thunder.
Batch of Y36-48 Stringers

Station 5.1 Splice

120 Ton Press Brake at a near by shop